CORE Team Master Plan Report to the Board

Since our last Board meeting in March 2012 the CORE team consisting of Robin Morris, Kinny Perot, John Connell, Kate Stephenson Kathy Meyer and Abby Martin have met weekly focused on reconciling the master plan and applying for Town and State Permits.

The attached current version of the master plan shows the known conditions and constraints including wetlands, steep slopes, stream setbacks, zoning setbacks etc. The building forms are “principle gesturesand have not yet been designed.

The CORE teams focus has been on defining the build constraints of the proposed master plan and to
this end the following field teams have been established:
    Forest, Agriculture, Wildlife, Wetlands Kinny Perot, Abby Martin, Dave Warren, Buzz Ferver, Aaron Locker
    Ground & Storm Water Kinny Perot, Andres Torrizo, Tony Stout, Maeve McBride, Peter Lazorchak, Ethan Timm
    Waste Water Robin Morris, Pete Munoz, Peter Lazorchak, Malena Marvin, Barton Kirk, Harold Leverenz
    Design & Plan John Connell, Kathy Meyer
    Energy & Solar John Connell, John Ringel, Jeff Schoellkopf, Andy Shapiro, Kate Stephenson, Jesse Cooper

In January, the school submitted an application to the Waitsfield DRB for sketch plan review and plans to submit a detailed site plan application by July 24th (6 months after sketch plan review). The next review is a twostep approval process and we anticipate that dialogue with the DRB during the first step will result in additional reconciliation and data generation prior to the final review.

Critical to our permit is the approval by the DRB of “design criteria” for the buildings in phase I & II that will allow a Semester Course to design/build a building without returning to the DRB for any approvals. This was discussed in the DRB at sketch plan review and will likely be a lengthy discussion.

On approval of a permit from Waitsfield DRB, the next step is an Act 250 application together with
other supporting permits.

Once we receive the Act 250 the school will be in a position to decide whether to move forward with Phase I of the build out including:
Phase Ia              Greenhouse Phase 1b       Intern housing  
Phase 1c                Semester Studio/Workshop and student accommodation

Applying and receiving Town and State permits for the master plan is critical to the school for the
following reasons:
    The Towns Adaptive Reuse Overlay District requires a master plan
    The master plan provides a context for decision making of any built form on site
    Additional permitting does not work for onsite semester design build projects  
    Master Plan provides clarity for the future of the School
    The current waste water system will require moving to a replacement field

The financing of the master plan was from restricted funds specifically donated for Master Planning.

In summary, whether or not the school moves forward with the entire buildout, a permitted master plan is critical to ongoing decisionmaking.  The CORE team is committed to finishing this current stage of permitting and look forward to further discussion at the forthcoming board meeting.

Current iteration of master plan as of 6-12-12
 